Risk Treatment Methods
Question 3
Risk Treatment Methods
1.The project team is developing an app for iOs, Android, Windows and Blackberry phones. The
development team lead identifies a risk with the Blackberry phones. She says that the team have no
experience with Blackberry, and the Blackberry operating system is not capable of performing many
of the required functions. You recommend to the client that “Blackberry” compatibility be removed
from the project. The client agrees. Which risk treatment method is this? Explain your answer.
2.Which risk treatment method should be used when a section of the project is too difficult for the
company to perform? Explain your answer.
3.You are managing a project which uses subroutines and libraries from a number of different
sources. You are concerned that the project might accidentally contravene the law. So you ask the
HR department to employ someone with specialist knowledge in the area. Is this an example of
“Transference”? Explain your answer.
4.What is the difference between “Avoidance” and “Acceptance”?